Monday, June 20, 2016

Why you need a budget

So you have decided to take on a construction project.  You have a clear vision of what you want and you have a dollar limit in mind for the work.  Are you ready to move to the next level? 

If you have not sat down to estimate the cost of your vision the answer is no.

It is important to note that an estimate and setting a dollar limit are two different things.

Your budget should not be based simply on how much money you have available.  Your budget should be based on a well-developed estimate that meets the scope of work you want.  

You will need to do a little legwork in order to be ready to develop your budget. 

Make sure to invest in preliminary studies and conceptual designs to document your vision. 

Don't be discouraged if your first concept comes in higher than you expected.  There are a number of design options to help lower costs without compromising your vision.  Work with your concept designer to modify your concept until the design has been optimized. 

If your optimized design still exceeds your available funding you have three options:
1. Shrink your program.  If your vision was too grand, you might want to consider a smaller version of your vision.  Perhaps you can do with less square footage or one story instead of two.

2. Phase your project.  Do you need everything all at once to operate, or can you build a portion now and the rest later?  Consider a phased approach which allows you to begin operating while you generate revenue and save for phase 2.

3. Can you secure financing?  There are a number of financing options that can help you reach your dreams.  Perhaps you can finance the cost of the project and actually hang on to more capital.

Preparing an estimate will arm you with the information you need to anticipate your funding needs.   You don't want to start the project unless you know you have the funds to finish the project and you wont know this without an estimate.

Let me know your thoughts and write me if you have questions.

Monday, June 13, 2016

How to avoid change orders on roof replacement

A couple recently came to me upset that they were forced to accept a change order on their roof replacement project.  The value of the change order was 50% more than their initial quote. 

The contractor presented them with the change order only after their existing roof tiles had been stripped off the roof.  He told them that the change order was for extra unknown work required by the local building code.  He said that he could not install the new roof without first replacing the existing plywood decking.  A local fire ordinance required fire rated plywood that was installed prior to 1992 be replaced with new fire rated plywood.  The house was built prior to 1992 and the code requirements did apply.

The couple argued with the contractor which caused the contractor to call his men off the roof and stop the work. 

The couple stood their in front of their home with their roof exposed and a pile of old roof tiles on the front lawn.  The contractor produced his contract which excluded replacement of the decking and another document that cited the code regulation.

For anyone caught in this situation, this can be gut wrenching.  You have no choice.  The contractor could charge anything he wants and you would be obliged to pay.  The alternative would be to go back out and find someone else, but you would have to deal with an exposed roof and maybe even have to cart away the debris the first guy leaves behind.  Basically, there is no choice but to accept the change order and move on.

So what went wrong and how could this have been avoided?

First let's see what the couple did right.
This couple did solicit multiple bids, so they were not relying on a single proposal.  They did solicit quotes from local contractors familiar with local regulations.  In this case the couple also had unit pricing for new plywood, so the contractor had to honor that rate.  One would say they did go about this the right way.  They claimed that all of the solicited contractor's excluded replacing the plywood decking.  They all stated that they could not know if the plywood needed to be replaced without taking up the tiles.

There are a number of subtle changes that this couple could have made which would have resulted in better results.

1. They failed to request the proposal on the same bidform.  When they solicited proposals they did not present the contractors with their own bid form.  This gave the contractors freedom to present their quotes in whichever format they chose.  In turn this made the homeowner's work of comparing the quotes more difficult.  Before you solicit a quote always create a bidform and require that the contractor presents their price on your form.  Ask for as much detail as possible.  I will post an article on how to build a bidform in the near future.

2. They failed to ask for a fixed price.  All of the contractor indicated that there was a chance that the plywood would have to be replaced.  In hindsight, it seems obvious that they all were aware of the local ordinance and simply were not forthright with the owner.  Anytime you have a potential for a change order, the way to deal with this is to ask for a fixed price (this is called an add alternate price), in this case the couple had a unit price.  Fixed prices are better than unit prices because a fixed price is more predictable.  Make sure your bidform includes a line item for add alternates, but make sure you describe the scope of the add alternate in as much detail as possible.

3.  They failed to invest in preliminary studies.  It may seem unreasonable to spend money on an architect for a simple roof replacement, but for a few hundred dollars, an architect could have informed the couple of the local ordinance and could have inspected the plywood from inside the attic to determine if it needed to be replaced.  In this instance the Architect's cost would have been less than 5% of the total cost of this work (inclusive of the change order).  The Architect could have also advised the couple on how to breakdown pricing on their bidform and helped draft the description for the add alternate.

These simple subtle changes would have saved this couple the gut wrenching drama they experienced.  I also think that they might have paid less overall (including the architect's fee).  Soliciting prices from contractors is more than picking up the phone and asking for a quote.  Even the simplest remodel or repair work deserves some level of investigation and preparation.

Tell me your stories.  Have you experienced similar circumstances?  Do you think these simple changes would have helped you?






Monday, May 2, 2016

Why Honesty is critical to a successful construction project

In the construction industry you have a lot of stakeholders and partners to work with.  This makes teamwork really important.  In order to foster a good team environment, trust is priceless.  Trust is built over many weeks and months of good will and cooperation, but trust can be broken in a single moment of weakness. 
Our human condition is inherently defensive.  It's common to behave evasively or defensively when we make mistakes, but in order to retain trust, we have to avoid reverting to this basic instinct. 

Although the repercussions of a mistake could be difficult to bear, the impact of obfuscating or deflecting responsibility has far greater implications.  Here are a few reasons why being forthright is the best policy.

Promotes problem solving
All projects encounter problems, the ability to promptly and effectively solve problems is critical to success.  When the team communicates honestly and completely with each other, problems can be mitigated.  Often when problems are revealed early, the impact of mistakes can be minimal.  Conversely, when problems are ignored or hidden, the issues becomes more difficult to overcome.  Communicate your mistakes promptly.  You may be pleasantly surprised when your team rallies behind you to mitigate your mistake so they have no impact at all.

Avoid conflicts
Nothing raises ire and frustration on a job site more than failing to own and acknowledge mistakes.  Conflicts on the job result when one person appears to make more work for others.  Revealing a mistake and owning the resolution of the mistakes is an effective way to avoid conflicts.  When others see you've been honest about your mistake, they are likely to respect you.  This helps them trust you and also promotes honesty from others.

Promotes good will and cooperation
When mistakes happen and you take responsibility for it, others appreciate you more.  Most can empathize with someone who makes mistakes because they know that one day it could be them.  When you own your mistakes, others are likely to help with its resolution.  The act of recognizing your error and then working to correct it shows you are honorable and trustworthy.  People naturally gravitate towards trustworthy individuals and makes them want to work with you.

Enhances quality results
The combination of good will and trustworthiness resulting from your honesty simply leads to higher overall results.  When people enjoy coming to work their work products is better.  An honest and cooperative work environment produces good results consistently. 

Regardless of whether the news is good or bad, being able to rely on accurate honest information is paramount.  Maintain your integrity throughout every project (even when things go bad).  Team members and colleagues will stick by your side when they know you can be trusted.  No one is expected to be infallible but honesty throughout breeds a positive and nurturing work environment that can overcome most problems effectively and with minimal impact.

I have communicated the benefits of honesty in the context of a construction team, but I think these benefits hold for all aspects of your life.

What do you think?  Are there times when you shouldn't be honest?  Were there times in your life where you were honest and wished you hadn't?

Monday, April 18, 2016

Design and Construction Work without a contract. The reason why Owner's should never allow it

Today I want to address the reasons why Owner's should never allow any work to be performed without a fully executed written agreement.

In Today's HGTV world where entire room renovations happen "While you were out" and "Restaurant Impossible" rebrands failing eateries in a weekend, the notion that construction should happen quickly is all too prevalent.  These shows don't reveal the pre-work that goes into performing these miraculous transformations and they don't account for the incredible amount of man-power that goes into these feats.  The most critical component of all of this work is the written agreements that must be in place for any of these projects to happen. 

Aside from the magical transformations that we are treated to on TV, it is all too common in the construction industry for Architects or Contractors to jump right into the work without taking the time to negotiate an agreement.  There are various reasons why these pros are so eager to get started.  For starters, you may have expressed a desire for a very aggressive project schedule, which they are all too happy to demonstrate how responsive they can be.  Maybe the scope of the work is exciting and they can't wait to get started.  Maybe they are short on work or coming off another project and they need the work.  Whatever their reason for wanting to jump right into your project, your reasons for not allowing this are stronger.  Take time to negotiate your agreement and don't skip any steps.

First, when you allow a vendor to start work you give up all of your leverage to negotiate.  Leverage is most important for negotiating pricing and favorable legal terms.  Without this leverage the Vendor has almost complete control over you.  This means you could be pushed into unfavorable agreements that limit your recourse when things don't go well. 

Written agreements are the prevailing document protecting both parties in the event of a dispute.  If you allow a vendor to commence the work or even perform the entire scope of the work without a contract you are relying on verbal communications between yourself and the vendor.  Verbal agreements are not only subject to interpretation, they are also prone to selective recollections.  Problems can arise at any stage of the project including very early on.  Don't allow any work to happen until you have things in writing.

Another reason Owner's should not allow work without a contract is that the scope of work needs to be carefully written and agreed to by both parties.  Without a well-written scope of work, you and your Vendor may have different interpretations of the scope.  Not only does this cause tension between the parties, but then it also opens the window for the Vendor to ask for more money.  

These three critical concepts illustrate the reasons why you should never allow anyone to perform any work without an executed written agreement.  It is too easy to get caught up in the urgency of a project.  Owner's need to take disciplined measures to ensure that they have all the protections possible before any work begins.  Expediting or skipping the contracting process puts Owner's at great risk.  Projects that are allowed to go on without written agreements tend to be more contentious, they cost more to complete, and can actually take longer than projects that are contracted.  Take the time up front to agree on the scope, schedule, cost, and legal terms and your project will run more smoothly and if you have any issue, you will have a basis for resolving whatever comes your way.

Tell me about your experience.  Have you done work without a contract?  Was it successful?  

Monday, April 11, 2016

Building Rules and Regulations for your home construction project.

I've just published my first Article for the year.  The topic I'm addressing this quarter is rules and regulations for a construction project.  I hope you find this helpful.  Here is an excerpt from the article check out my website to read the full text.


There are multiple level of clean-up required during a construction project. Each phase of construction should have clear rules about what you expect.

While construction is ongoing establish expectations to keep the floor free and clear of tools, screws, nails, or other tripping hazards.  Construction debris will be piled neatly until it is ready to be removed from the premises.  Appurtenances that are suspended above the work area will be safed and secured at all times.  Exposed wiring and plumbing lines to remain will be deactivated and safely secured in place.

Rules for daily end-of-day cleanup are also important.  The area of work will be broom swept daily.  No construction debris will be allowed to remain in the area of work overnight.  Tools will be collected and stored in a secure tool chest or carried off the job site daily.  Construction materials will be stored neatly in designated areas.  All electrical equipment will be unplugged from it's power source and stored in a secure designated location.


Check back next week when I return with my weekly blog.

Monday, March 21, 2016

Should you hire an engineer directly or through an architect


Just about every project requires the services of both an architect and an engineer.  In some rare exceptions you might be able to do a project with an architect and not need an engineer.  Such projects are generally simple alterations that don't impact any building systems, but If you are building a new house or adding a substantial addition to an existing house, it is likely that an engineer will be required.

Once the decision to hire an engineer has been made, you will need to consider how to contract the engineer.  Some might suggest the engineer should be hired directly by the owner, while others recommend contracting the Engineer as a sub-consultant of the Architect.  There are pros and cons to both options.

Acknowledging my bias as an architect, I hold a pretty strong view that the architect should always be the lead designer and the engineer should be subcontracted to the architect.  It is true that you will pay some amount of mark-up to the architect in order for them to subcontract the engineer, but for most projects the risk vs reward evaluation does not support hiring the engineer directly.

To fully appreciate this statement it is important to know that the coordination of the building systems is an essential part of the architect's responsibility. 

It may surprise some that architects are responsible for coordination of building systems, but the only licensed professional in the design team that is educated in all of the major systems of a building is the architect.  Engineers are specifically trained in their respective disciplines and tend to know their part very well, but they are generally not familiar with the other systems of the building.  It's critical that you have one central figure responsible for coordination of the design to avoid a large amount of costly coordination during construction.

If your architect does not have a contractual relationship with the engineer and the engineer does not have to answer directly to the architect, the architects authority over the engineer will be limited.  This may put the burden of coordination on to the owner and the owner could take on a needless risk and expense. 

We also need to recognize that the mark-up added to the engineer's fee will be minimal.  Also, most architects are generally willing to negotiate the markup, so if you are concerned about how much you are paying you can discuss this upfront.  Generally a 10% to 15% fee is common.  The lower the value of the engineer's fee the higher you should expect the percentage mark-up paid to the architect.

You may pay a bit more allowing the architect to hold the engineer's contract, but empowering your architect to coordinate the various parts of the project will pay dividends well into the construction phase of work.  What do you think?  Is it worth the additional mark-up for design phase coordination or would you prefer a lower design fee?


For more tips on how to manage your project, check out my articles on www.luisgile.com.

Monday, March 14, 2016

Best Practices for Managing sub-contractors

In most construction projects, sub-contractors represent the majority of the Cost of Work.  Most residential Owners spend no time considering who their sub-contractors are.  While it is not prudent to come between a General Contractor and his subcontractors, it is prudent to establish some parameters for accepting a subcontractor.

In considering the best practices for managing subcontractors, we need to keep in mind that the legal relationship is expressly between the General Contractor and the sub-contractor.  While you can and should establish parameters to govern who the General Contractor can hire, the final decision should ultimately be theirs.

Requiring that all sub-contractor's hold a minimum level of insurance is a must.  There are many trade contractors with little or no insurance and some GC insurances include provisions that could put you at risk if an insurable event occurs.  Speak with your property insurance carrier to establish what minimum insurance requirements you should require from the GC and his subs.

Request proof of licensing for sub-contractor.  This is not cut and dry, there are some trades that are not required to hold licenses.  Call your local Building Department to determine which trades require licensure and require that those trades that do, provide proof of licensure prior to award.

Request copies of the sub-contractor agreement.  The GC must have a written agreement with every sub-contractor.  The GC may be hesitant to provide you with his subcontractor agreements.  This is so because part of the way a GC makes money is by marking up the trade contracts.  The point here is not to uncover overcharges or to negotiate price.  It is important to see that a formal agreement exists between the GC and the subs and that the provisions of the the GC's agreement provide adequate protections for the Owner.  If your GC objects to sharing his agreements allow him to redact any pricing information from the agreements first.  This allows you to see the terms of the agreement without revealing too much of the GC's financials.

Establish communication protocols.  All communications should flow through the GC.  Dont ever give directives to a sub-contractor.  You must respect that the GC has to retain control over the site.  If you give a trade contractor direction to make a change without the GC's knowledge you will be compromising the GC's control over the job. There could also be gaps in the direction you gave which could impact other trades.

Its important to know just how much control is appropriate when managing sub-contractors. Too few controls could mean poor quality, unsafe working conditions, or illegally performed work. Too much control could delay your project, add cost to the work, or increase the owner's risk.  Strike a perfect balance and your project will benefit greatly.

What level of controls have you placed on your subcontractors? Do you feel you had too much or not enough?

For more tips on how to manage your project, check out my articles on www.luisgile.com.

Monday, February 29, 2016

How to ask a Builder for a quote

Asking a Builder to quote a project sounds like a simple task.  Most people put very little thought into requesting a quote, but taking this too casually could be a terrible mistake.

Your first formal communication with an Architect or a General Contractor is when you ask for a quote for your project.

If you don't take the time to communicate how you want the pricing to be presented, you could receive quotations that are difficult to compare.  In the construction industry, there is no standard way to present a quote, so while one bidder may provide you with a detailed quote, another may simply quote you one all-in number.  If you are not clear about how you want the quote to be presented, you may not be able to compare one quote to another.  This will make it difficult to discern which bidder addressed your scope completely and which one will be hitting you with change orders during the work. 

Another common oversight is soliciting a quote without a complete scope.  There are several ways that an Owner can (and should) influence scope.  When soliciting a quote from an Architect, there are several preliminary studies and preliminary design work that you should commission before you solicit a quote for construction documents.  When requesting a quote from an Builder, be mindful that the Architect's drawings alone will not fully address every aspect of your project scope.  If you fail to address all of the elements of the scope, assumptions will be made and you may not be pleased with the results.

Give yourself sufficient time to prepare.  Don't skip any of the typical phases of work.  Spend the time up front to understand your project scope before you make expensive commitments.  The cost of making a change can be as much as six times more expensive during construction phase than it is during design phase.

If you follow these basic steps;  you will be more confident when you solicit your quotes, bidders will know you are serious, you will have bids that can be readily compared, and you will have all you need to make an educated award decision.

What information did you request in your solicitation? Were you able to compare bids? Was your scope clear and complete, or did you deal with several change orders?  Tell me your best or worst experience.

Monday, February 22, 2016

Are you a Project Manager

One of the most important yet commonly overlooked roles in residential construction is the Project Manager.

Owners know they need a builder and most recognize when they need an Architect but few ever consider hiring a Project Manager.

This results in the Owners taking all of the duties and responsibilities of the PM without even knowing.

This gap in the project is felt by all of the team but typically is most detrimental to the Owner himself.

This results in; increased fees, delays in schedule, and poor workmanship.  In addition, Owner's typically come away with a general sense of being overwhelmed and often other members of the team are blamed.

The Project Manager plays a key role in the project team.  The PM has a number of responsibilities.  Getting the most out of a PM means that the procurement of the PM should meet a few key conditions.
     1. The PM should be an experienced construction professional.
     2. The PM should have no affiliation with any of the project team. 
     2. The PM should be hired directly by the Owner.

The Project Manager's role is to act entirely in the owner's interest.  The PM drives scope, schedule, and budget on behalf of the Owner.  Employing an independent professional to work in your best interests can greatly reduce the stress of a construction project.

Follow these simple suggestions and you will reap the benefits of this important member of your project team.

Are you acting as your own Project Manager?  If so, how are things going?  Did you hire a PM and find they were not as helpful as you expected?  Write me and tell me your experience.

Monday, February 15, 2016

Find your builder match

Finding a Builder can be an overwhelming and scary task.

There are many sources where you can find a builder, but making sure he's the right one for you isn't an easy task.

Don't settle for the first guy that answers the phone.  Keep searching until you have at least three viable firms.

Do your due diligence by asking questions and calling references. 

Don't work with anyone who makes you feel intimidated or uncomfortable.

Don't loose sight of the fact that you are the Client.  You are not expected to know construction.  Anyone that acts condescending or does not take the time to walk you through things is not worth considering.

Above all, no matter how large or small your project find someone you feel comfortable with, but don't skip calling references or verifying licenses and insurances.

Were you successful in your search?  How did you find your match?  Did you make a bad choice?  What steps did you skip?

Saturday, February 6, 2016

What's new for 2016

Happy New Year everybody!

Yes, I know I'm a little late, but better late than never.

Im going to start 2016 in a slightly different way.

If you were with me from the start (launched my website in March 2015) you will note that the content and design of my site has evolved quite a bit.

From the start, I wanted my site to be a place where you could find articles full of in depth content to help you manage your projects more effectively.

I feel pretty good about the current state of the content and the design of the website so I want to shift my focus to shorter more frequent blog entries. 

My hope is that this shift will allow for more of a quick read along with more interactions between you and I.

I will still be producing articles (like the ones I published in 2015) but there will be fewer of them. 

I would love your feedback on this approach. 

Do you prefer long articles with lots of content or blogs that offer a quick snapshot on a single topic?

Saturday, November 21, 2015

How an Owner can influence Scope definition

How an Owner can influence Scope definition
By Luis Gile
November 2015

One of the most important factors in the success of a construction project is having a quality Scope of Work.  Scope of Work is the definition of what you expect your service providers to do for you.  A service provider could be an Architect or a Contractor.  You should have a Scope of Work for every phase of your project and for every service provider.

Owners have a great deal of influence over the Scope of Work.  The steps an Owner takes (and even the steps an Owner skips) could have profound influence over the quality of the Scope of Work and ultimately the quality of the final product.

In this article I will outline some of the ways in which an Owner can influence the quality of the Scope of Work.

Number One:  Invest in Preliminary Studies:
There are a number of preliminary studies that an Owner should undertake before beginning design.  The first and most important one is a Programming and Feasibility study.  Most of the time this is done as part of the schematic phase of work.  Assuming that this will be done and that it will be done correctly could be a costly mistake. 

This type of study has two parts.  The first is the project programming.  This establishes the basic parameters of what you want to build (for example, 2 bedrooms, one bath, and a garage).  The second part of this study is the code and zoning review.  A code and zoning review establishes the limitations of your project, this is absolutely necessary to establish the feasibility of your project.  It is a good practice to have this study done as a distinct phase of work.  I recommend that you pay a small fee for this study and share it with all of the Architects you wish to consider so that you can establish a common starting point for all. 

There are a number of additional specialty reports and studies that you might also need.  Geo-technical Reports, Site Surveys, and building conditions reports might be needed depending on your project.  If you attempt to proceed without the proper preliminary studies, it is possible that you may have to pay for additional services later on or face steep penalties for violations.

Number Two:  Invest on Schematic Designs:
Schematic Design (also called conceptual design) is a phase of work under which a Designer will work with the Owner to design what they want.  This is the phase where you can change your mind as frequently as you would like without incurring huge costs. 

A lot of people rush right into construction documents because they think they know what they want and think it will save them money.  Unfortunately, most people do not realize that the cost of making changes later in the process can be more than 10 times the cost of making the same change during schematic design.  If you invest a little more time and money up front to refine your design the next phases of work will run much more smoothly.

Number Three: Establish your contract terms:
There are a number of options for establishing the contract terms for a construction project.  Most of the time Contractors will use a third party template from the American Institute of Architects or from Consensus Docs (produced by the Associated General Contractors of America). 

I recommend that you consult with a Construction Attorney before you accept any form of agreement.  You should note that just because these are considered "templates" does not mean that they cannot be modified or that these terms are right for you.  An Attorney skilled in construction will be the best person to advise you on which terms to accept.  Regardless of which template you use and how your attorney decides to modify them, make sure that you establish these terms up front.  Do not wait until you are ready to award the work to decide on which template to use and don't try to interpret these contracts on your own.

Number Four:  Define the General Conditions:
The General Conditions of Construction are terms that establish the services that the Contractor will be required to perform.  General Conditions are often overlooked or added in as an after-thought, but these are the most important part of the Construction Documents. 

Your Architect's drawings will tell the General Contractor what to build, the General Conditions tell the contractor how you want the project managed.  You should review the General Conditions well before you solicit pricing.  Make sure that you establish clear expectations with respect to meetings, reporting, scheduling, and cleaning.  Ultimately, the Owner has the responsibility for making sure that the General Conditions are aligned with their expectations.  You should not expect your General Contractor to perform these services the way you want them unless you communicated them clearly up front.

Number Five: Establish Close-Out Procedures:
Closeout Procedures refer to the final steps that the General Contractor or possibly even your Architect will have to perform in order to receive final payment.  Close out procedures are often part of the General Conditions, but I have called these out specifically because these are very important. 

You need to be very careful here.  If you release final payment before all of your closeout procedures have been completed you may find yourself missing critical documents.  One of the most overlooked items is the lien waiver.  Lien waivers are documents that prove you paid the contractor and that the contract acknowledges receipt of the payment.  Your close-out procedures should require a lien waiver for the full value of the work (including change orders).    Without this document if a contractor places a mechanic's lien on your property, it will be more difficult to lift the lien.  This will make it impossible for you to sell or refinance your property.  Other documents that you might need are warranty's for labor and equipment, release of surety if you had a bond, or inspection approvals from the local authority.

These are just some of the things that an Owner can do to make sure that their scope of work is as good as it can be.  Consult with a professional if you are unsure of anything and keep in mind that no scope of work will ever be perfect.  These are the challenges of construction and this is why you need to be vigilant and careful through every step of the process to make sure that you make as few mistakes as possible.

What steps have you taken to influence your scope of work?  Have you overlooked any of these and had a tough time? Email me with your experiences.


Saturday, September 5, 2015

How to develop a budget for your construction project (Part 2)

How to develop a budget for your construction project (Part 2)
by Luis Gile

Building on the basic information we discussed in Part 1, we can now move forward with developing our project budget.

First lets talk about the various estimating methods that we can use.

Estimating methods
There are several methods for estimating projects.  The estimating method you choose will be determined by how well your scope is defined.  It is perfectly acceptable to change your estimating method as your project advances.  In fact I highly recommend that you revise your estimate each time your scope changes or becomes better defined.

At the earliest phases of work, your scope definition is very limited so your estimate will be less detailed and you should have a greater margin of error and contingency.  As the scope gets further defined, estimates become more detailed and should have lower margin of error and lower contingency.

The types of estimating methods I will cover are:
1. Area Pricing 
2. Unit Pricing
3. Budgetary Quotations
4. Percent Cost of Work

Regardless of the type of estimating method you choose, all estimating methods require two pieces of information.  The first piece of information is the scope.  The second piece of information is the market rate.   

Area pricing
Area pricing uses the area of the space you want to build multiplied by a cost per area.  This pricing method can be used for either hard costs or soft costs, but it's most commonly used for hard costs.  We use area pricing when our scope of work is very limited.

The only scope information needed to use area pricing is the approximate area of the space you want to build.  In the United States the unit of measure we use for area measurements is square feet.  We can use the project program we discussed in Part 1 to estimate our area.

The market rate needed for area pricing is a cost per square foot.  The cost per square foot is affected by a number of factors including, the type of project, your geographic area, and the scale of the project.

Unit Pricing
Unit pricing can be used in a variety of ways.  Most often unit pricing is used when the scope of work is more detailed and well defined.  

Scope definition for unit pricing typically requires a detailed set of design drawings.  If you have detailed design drawings you can use the drawings to perform material take-offs.  The term "material take-off" is a method of estimating material quantities by taking scaled dimensions off of design drawings.  

Market rates used in unit pricing are typically specific rates for materials, equipment , and labor.  Unit pricing can be collected from a variety of sources including directly from suppliers and also from historical pricing.   

Budgetary Quotations
Soliciting budgetary quotations directly from trade contractors and material suppliers is another common method of cost estimating.  Soliciting budgetary quotations can be even more accurate than unit pricing but can take longer than other methods.  

The scope of work for this estimating method can vary greatly from very little scope definition to a very detailed set of design drawings.  The value and accuracy of budgetary quotations varies equally with the amount of scope definition.  It's also common to rely on the trade contractor to perform the take-offs for his specific trade.

You wont need any market rates for this estimating method because the budgetary quotes will come from each trade contractor.  All you need to do is add each contractor's price together.  When you use budgetary quotations it is important to ensure that there are no gaps in scope between trades contractors and that each contractor is clear about what scope they need to quote.

Percent Cost of Work
Percent Cost of Work rates use rule-of-thumb percentage rates to estimate soft costs.  

This estimating method is dependent on having an estimate of your hard costs.  You can use any combination of the previously discussed estimating methods to estimate your hard costs.

Once you have your hard costs estimated, you can apply the percentage rates to estimate your soft costs and then add the hard costs and soft costs together.

Hybrid pricing
It is common to use a hybrid or blend of these options.  How you combine these methods is entirely up to you.  

In this article we will focus on a hybrid approach that uses area pricing for hard costs and percent cost of work for soft costs.  This blend of pricing methods is the simplest and most effective way to budget a project at an early phase of development.

How to budget
If you have been following my blog you may recall the May 2015 entry entitled "What are the phases of work of any construction project".  In that article we took a step by step approach that began with high level scope definition and methodically made our way through design.  When planning and executing a project we always begin with design and we add layers of detail until we know what we want to build.  The construction work is always the last step.  For budgeting we actually start backwards.  

We will be using percentage of cost of work rates to estimate our soft costs, so we will need the Cost of Work as our multiplier for these rates.  Establishing the Cost of Work up front will also help us understand the scale of the work we are taking on. 

First we'll estimate the hard costs using your program's estimated square footage (established when you developed your program) and a cost per square foot market rate.  The math on this is pretty simple, simply take your estimated square footage multiplied by the area market rate

EXAMPLE:

From Part 1 we estimated the program to be 421 SF

Estimating your hard costs
To estimate your hard costs, we will need a cost per square foot market rate.  

All area pricing rates will be based on historical rates.  These rates are highly influenced by the location, date, and scope of the project that the rate is based on.  in other words, if you use a rate from a garage addition in New York from 5 years ago and your project is a kitchen addition in Kentucky that you expect to start one year from now, you wont have an accurate budget.  Try to find rates that are as closely matched to your specific circumstances as possible.

I recommend getting at least three area market rates and averaging the three together.  This eliminates any guess work and gives you the best chance at using an accurate figure.

Here are a few sources that I recommend.  You can type in "cost per square foot" into your web browser and I'm certain you will find others.


For this example, we will use an area market rate of $200 per square foot.  Now we multiply the square footage by the area market rate as follows:

421X 200 = $84,200

Therefore our hard costs for this project are $84,200 eighty-four thousand two hundred dollars.  This is the cost of the labor, materials, and equipment needed for the project.

Estimating soft costs
 For the soft costs of this example we will focus on estimating Architectural fees, contractor fees, and general conditions costs.  These costs are the most common soft costs applicable to most projects.  

We will use percent cost of work rates to estimate these costs.  These rates are typically within the following ranges.  The specific rate you use is dependent on the location and scale of your project.
1. Architectural fees, (6% to 15%)
2. Contractor fees, (5% to 15%)
3. General conditions costs,  (10% to 20%)

If we use the $84,200 estimate for our hard costs we can estimate the following:
Architectural Fees (15%) = $12,630
Contractor Fees (15%) = $12,630
General Conditions Costs (10%) = $8420

Sum up your costs then add contingency and margin of error
          We now add up all your costs and add our contingency and margin of error
          Hard Costs...................................$84,200
          Architectural Fees........................$12,630
          Construction Management Fees....$12,630
          General Conditions Costs...............$8,420
          
          Subtotal....................................$112,000

          Owner's Contingency (@15%) .....$16,800
          Margin or error (@20%) .............$22,400

          Total Budget.............................$151,200

Keep in mind that the "Owner's Contingency" and the "Margin of Error" are essentially funds that you need as safety nets.  These costs are not to be shared.  You and maybe your Project Manager (if you have one) should be the only people who know you have this money set aside.

Never reveal your budget to your Contractor and when you speak with an Architect about your project, reveal only your estimate for the hard costs.  When an Architect asks for your budget, what they want to know is whether you are looking for higher end finishes or a basic design, so giving them your estimated cost for hard costs should suffice.

Now you should have enough information to develop your budget.  Let me know how well the process works for you and when your project is completed, email me back to tell me how close your numbers were.

Wednesday, July 15, 2015

How to develop a budget for your construction project (Part 1)

How to develop a budget for your construction project (Part 1)
By Luis Gile

Developing a project budget is one of the most important early steps of any construction project. This will be a multi-part series that will give you the background and information you need to develop a budget for your project.

Taking the time to develop an accurate budget is an essential step prior to contracting an Architect or a General Contractor. This will ensure that you have the capital to complete your project and that you don't commit yourself to any contracts without knowing your spending limit.

Before you begin building your project budget, there are specific pieces of information that you need and some concepts you should understand. In this first article we will go over the basics so that you can have good foundation for starting your budget.

Project Program
Before we begin budgeting, we have to estimate how much space we need. We can do this by by developing a project program. Your project's program is a list of spaces with critical design information such as square footage, adjacencies, and other specific requirements. I will publish a more detailed article about how to develop a program in a future blog.

For now, to simply estimate your square footage, note down all of the spaces you want with an approximate width and length of each room. Multiply the width and length for each room to come up with the square footage for that space. Add up all of the square footages for all of the spaces you need to determine the total footprint of your new space.

The best way to estimate the size of a room is to consider the furniture you will be needing in each space and then adding an appropriate amount of space for circulation. For example a dining room should be large enough to accommodate a dining table, chairs, and at least one hutch or credenza. The clear space around the table should be no less than 4 feet, but if you want a more comfortable space, you may choose to add 5 feet or more. You may also want to add an additional 10% to 15% more square footage to the total to allow for structure and connecting space between multiple rooms.

Here is a sample list for reference:
Galley Kitchen........10 feet wide 15 feet long......150 square feet
Dining area............12 feet wide 18 feet long......216 square feet

TOTAL SQUARE FOOTAGE................................366 square feet
Circulation 15% of total.................................... 55 square feet

Total program..................................................421 square feet

Adjust the room names a sizes to suit your project. Once you are armed with this information, we can move on to the next concept.

Margin of Error
Margin of error refers to how much higher or lower your actual project costs will be from your budget. Margin of error is meant to account for fluctuations in cost and or square area. During early stages of a project it is common to assume that any cost estimate will have a 20% to 25% margin of error. To account for this margin of error, your budget should include a line item specifically called "Margin of Error".

As you get closer to the start of construction, your margin of error can be reduced. Keep in mind that an estimate is always just an estimate. There is no such thing as a 0% margin of error on an estimate, so no matter how accurate you think you are, always carry a margin of error in your estimate.

Contingency
Contingency is a word used to add monies to a project to cover the cost of unknowns. Contingency is different than margin of error in that contingency is meant to capture things your budget missed. 

The word contingency may be used by contractors, estimators, or even architects. The use of the word has different implications depending on who is using it. I mention this only to convey that when we talk about contingency for your budget, we are talking about the "Owner's Contingency". Owner Contingency is meant to cover hidden conditions of the site or other unknown costs of the project. This is not a fund for making changes to the scope. This is your safety net for completing the work.

As the Owner, you have a responsibility to pay for the services, labor, materials, and equipment needed to complete the work. Failure to make payment to any service provider places you and your property at great financial risk. As such, you have an obligation to ensure that you have sufficient financing to cover all costs. You don't want to find yourself 3/4 of the way through construction only to realize you have run out of money. Make sure you carry 15% to 20% of Owner's contingency throughout the project. This is over and above any margin of error.

Also, please make sure that your contingency is fully funded. This means that you either have the capital or sufficient financing to cover the contingency. It's not enough to include the line item on your budget, you must also have the funds set aside and ready to use if needed.

Cost components
Your project budget will include a combination of estimates to cover hard and soft costs.

Hard costs refer to the cost of construction.
Hard costs include the following:
1. Trade labor such as masons, carpenters, plumbers, etc.
2. Material costs such as concrete, wood, light fixtures, etc.
3. Permanent equipment such as boilers, air conditioners, water heaters, etc.
4. Temporary equipment such as cranes, scaffolding, etc.

Soft costs refer to all of the other costs of the project.
Soft costs include:
1. Architectural fees,
2. Contractor fees,
3. General conditions costs,
4. legal fees,
5. real estate fees,
6. cost of land acquisition,
7. permit fees,
8. zoning fees,
9. filing fees.

We will begin our estimate with the hard costs first and then use the hard costs as a basis for estimating the soft costs.

With these basic concepts in mind we have set the stage for developing your project budget.

In my next entry, I will go over the various estimating methods that we have at our disposal and then go over a few examples of how we can apply these methods. Please join me again next month where we will continue to explore how to develop your budget.

Monday, June 15, 2015

Top 10 questions to ask a Contractor's References

Top 10 questions to ask a Contractor's References
By Luis Gile

Most people know that one of the best ways to qualify a contractor is to request references, but most never actually call. It might be that some think call a reference is a waste of time or possibly that you are imposing on the reference, but it is surprising how willing some folks are to share their experience if you simply ask. It should be noted that not every reference will be as accommodating, but even if you get one willing person, the information you can glean could be critical.

Make sure that before you call the references you are prepared with a list of specific questions. You should make sure that you ask every reference the same questions. This is the most effective way to compare references from multiple contractors.

Feel free to come up with your own specific questions, but here are ten questions you might want to ask.

Question number 1: "If you were to take on another project, would you hire the contractor again?"
This seems like a simple question that might not get you much information, but you have to listen carefully. A good deal of hesitation before their response or some qualified response should give you pause. Also, there might even be some who will honestly tell you that they would not want to work with this Contractor again even if they felt that their project was successful. Make sure to ask follow up questions depending on what they say.

Question number 2: "During your project which person from the Contractor's Company did you interact with the most?"
The goal of this question is to get a sense of who you will be dealing with during the project. Many times a Contractor has different folks that handle different parts of their business. This is not by itself a concern, but if the reference tells you that they mostly dealt with someone other than the person you have already met, you might want to go back and confirm who that person will be and meet them yourself. A construction project is a long term relationship. If you are not comfortable dealing with a particular person, you should reconsider awarding them the work.

Question number 3: "Would you say that the job site was kept in a neat and safe manner throughout the construction?"
Now we are getting to the heart of the matter. This question starts to explore how well the Contractor manages the job site. Keep in mind that you will be living with whatever mess the Contractor leaves behind at the end of each work day. Obviously this is a lesser concern if you are building a new house on a plot far from where you live, but even in such cases, the neatness of the site is closely tied to job site safety and that can represent a risk for the Owner.

Question number 4: "Were there any accidents during your project that caused damage to people or property?"
Similar to question number 3, it is important to know how safety conscious the Contractor is. Asking about accidents is a very specific way to understand how the Contractor manages the job site. If the reference tells you that there was some kind of an "incident", you need to follow up with, "Tell me how the GC handled the incident?". Listen carefully. You should hear that he stopped the work, contacted EMS, secured the job site, and implemented some kind of corrective action. Accidents happen, so don't automatically disqualify someone over this. The way they handle such matters can sometimes be as important as what they did to avoid an accident.

Question number 5: "During your construction project did you have any disputes over invoices? if so how were they resolved? "
The response to this question will give you insight into a couple of things. First it gives you an idea about the contractor's billing practices and second it tells you how easy the contractor will be to work with. It is common to have differences of opinion when it comes to how much is due on a construction invoice. The reason for this is because a contractor's invoice should be based on what percentage of work has been completed. No two people (especially an Owner and a Contractor) will ever agree on the percentage of work complete. The Owner usually thinks its much lower and the Contractor usually thinks it's much higher. So invoice disputes don't automatically equal "bad contractor". However, a Contractor should compromise somewhat with the Owner when there is a dispute. Also, the contractor should have all his back-up documentation available so that the two can sit and review what is due. An owner should never feel that they overpaid or were bullied into paying more than they felt was fair. If the Contractor has all of his ducks in a row, they should be able to justify everything on their invoice.

Question number 6: "Was the contractor present during inspections from the building department?"
To me a "No" response here would yield a "NO-GO" decision about hiring this contractor. There is nothing more basic and simple than being there for inspections. This is not the Owner's responsibility and any contractor that chooses to not be present during an inspection should not be considered.

Question number 7: "Did the contractor provide you with a construction schedule? If so, were you kept up-to-date with schedule changes?"
This is important because without a schedule your project could seem like a never ending saga. Even if you have already requested a schedule from your contractor, knowing whether the contractor makes a practice of providing a schedule for other Clients will give you insight into how well organized and communicative the contractor will be during your project. The second part of this question is also important. Updating schedule changes is critical to managing a construction schedule. Knowing whether you can count on that for your project will give you peace of mind.

Question number 8: "With respect to changes to the work that affected the cost of the project, would you say that the you were well aware of the scope and the cost of all changes before the work was done?"
A good contractor should never perform any additional work without making sure that the Owner has agreed to the changes and approved any additional charges. If the reference does not give a definitive "Yes" to this question, beware.

Question number 9: "How would you characterize the contractors response to questions you might have had on change orders?"
All too often, contractors get defensive and uncomfortable anytime they are questioned about change orders. A grounded professional with nothing to hide, will not. You should be able to sit down with your contractor and review every item on a change order. If the reference suggests that the contractor was evasive or failed to clearly communicate about change orders, you should be concerned.

Question number 10: "How did you find this contractor?"
This question is really just to make sure that the reference you called is not a relative or close personal friend of the contractor. If they are in any way related to the contractor (other than professionally) you should consider this to be very weak reference and you should be suspicious of anything they said about the contractor.

Those are some of the questions that I recommend asking references.

Feel free to add to these or ask follow up questions depending on the responses you get. In all, I would say that your time on the phone with each reference should be less than 20 minutes. If you take any more time than that, the reference may start to feel imposed upon. Regardless, make the call, you are bound to get some good information.

Have you made a call to a reference? What key questions did you ask? How useful would you say calling a reference was in your decision making?

About my blog
This Blog is designed to help small business owners and residential homeowners manage their design and construction project more effectively. My goal is to communicate the best practices of design and construction and arm you with information to help avoid common mistakes.

About Me
I am a Registered Architect with over 20 years of design and construction experience. I enjoy working directly with Owners to help them meet their goals and objectives.